NEW PRODUCTION RATE OF MILL BASED ON NEW BLAINE SIZE- Formula 1

 NEW PRODUCTION RATE - MILL OUTPUT VS. BLAINE

formula -1

You can calculate the new production rate of ball mill based on the new blaine size, you just need to input following parameters:

1. Old Production rate
2. Old Blaine
3. New Blaine

you can also calculate the following mill calculation-Click Below


Calculate New Production Rate
Mill Output Vs. Blaine
Input Data: FORMULA -1
1 Old Production rate in TPH OPB
2 Old Blaine in cm2/gm OB
3 New Blaine in cm2/gm NB
Formula:
New Production rate- Mill output Vs. Blaine in TPH
OPB
Exp ( ( NB - OB ) * 0.49 / 1000 )
Calculation
Old Production rate in TPH 170
Old Blaine in cm2/gm 3000
New Blaine in cm2/gm 3200
170/EXP((3200-3000)*0.49/1000)
154.1 TPH